We were able to install the handrail brackets for the balcony of the stairwell (using 1/4" dia x 3-1/2" long lag bolts), cut and fit the handrail and cut and fit the landing pieces at the base of the overlook. The base of the iron balusters will fit into the landing pieces. Brent did not like the 1-3/4 inch overhang and routered each piece such that the overhang is only 1-1/4". Then each of the handrails were chiseled to have the brackets fit flush.
Then the final coat of green paint was applied to the stairwell wall and it looks great. Then the trim pieces were installed over the columns and doorway and then Brent added some additional molding pieces. The nail holes were filled using wood putty along with any gaps. Then the sander was used time and time again until the finish passed inspection. Several times the paint was applied and after inspection the sander was used again, painted, checked and some instances the process started all over. When for the weekend, the sander was put away.
We did accomplished a lot this weekend but we were slowed somewhat as Brent had back problems this weekend. Nothing serious, but enough to slow things down. Hopefully we will obtain the iron balusters this week and installed the upcoming weekend.
The final coat of paint on the stairwell wall. |
After installing the brackets the handrails were fitted. |
All the handrails on the balcony overlook were fitted. |
JoLynn touches up the stain and applies the polyurethane. |
After application of two (2) coats of polyurethane. |
The trim work of columns and passageway. |
The header applied to the trimwork. |
After sanding and applying the primer. Our attempt to imitate the Parthenon. |
After inspection, some areas needed to be sanded again. |
The backside of the columns and passageway. |
WOW, the work is coming along great.
ReplyDeleteGOOD JOB!!!!!!!